I am researching a strange finish variance on a project. The Finish Date on
a task is 8/5/05 and the Baseline Finish is 8/5/05. The Finish Variance is
showing as
-0.03 days. This is occurring throughout the project on various tasks with
an overall Finish Variance of 21.66 days when it should only be 15 days. I
have been informed that the plan and tasks have been properly baselined.
How do I find out what is causing this strange variance? Could
predecessors/successors and/or the completion of tasks be a cause?
Thank you very much for any assistance you may be able to provide.
a task is 8/5/05 and the Baseline Finish is 8/5/05. The Finish Variance is
showing as
-0.03 days. This is occurring throughout the project on various tasks with
an overall Finish Variance of 21.66 days when it should only be 15 days. I
have been informed that the plan and tasks have been properly baselined.
How do I find out what is causing this strange variance? Could
predecessors/successors and/or the completion of tasks be a cause?
Thank you very much for any assistance you may be able to provide.