S
SonOfPirate
I have a schedule that was purposely created to be dynamic in that I only
entered the initial work for each task then setup the schedule using
dependancies and constraints. Once the schedule has been created, I set a
Baseline so I have something for comparison later as things change. When a
task is begun, I set the Actual Start value and periodically update the
Actual Work field based on timesheet submissions. When the task has been
completed, I set the Actual Finish value.
Seems pretty straight forward except that the Work and Actual Work fields
change when I set the Actual Finish value.
For instance, I create a task that is expected to take 4 hours to finish.
My default Duration is in hours, so the Start and Finish Dates setup
properly. I set the Actual Start date to 5/8/09 and begin accruing hours in
the Actual Work field. If I accrue 3 hours (Actual Work), then set the
Actual Finish to 5/25/09, Actual Work changes to 4 hours and Duration is 96
hrs?. I don't want the Actual Work value to change!
Even more confusing is the case when, using the same setup, I accrue 4 hours
(in Actual Work) then set the Actual Finish date to 5/25/09. In this case,
the Actual Work (and Work) fields change to 64 hours?!?!?
Can someone shed some light on what is going on here? I can understand the
Duration value changing when I reset the Actual Finish date, but why is the
Actual Work value changing? And in the first case, why doesn't Work change
to match Actual Work when the task is "closed" by setting the Actual Finish
date? In my mind, the Actual fields should be immutable with the exception
of the Start-Finish-Duration relationship.
entered the initial work for each task then setup the schedule using
dependancies and constraints. Once the schedule has been created, I set a
Baseline so I have something for comparison later as things change. When a
task is begun, I set the Actual Start value and periodically update the
Actual Work field based on timesheet submissions. When the task has been
completed, I set the Actual Finish value.
Seems pretty straight forward except that the Work and Actual Work fields
change when I set the Actual Finish value.
For instance, I create a task that is expected to take 4 hours to finish.
My default Duration is in hours, so the Start and Finish Dates setup
properly. I set the Actual Start date to 5/8/09 and begin accruing hours in
the Actual Work field. If I accrue 3 hours (Actual Work), then set the
Actual Finish to 5/25/09, Actual Work changes to 4 hours and Duration is 96
hrs?. I don't want the Actual Work value to change!
Even more confusing is the case when, using the same setup, I accrue 4 hours
(in Actual Work) then set the Actual Finish date to 5/25/09. In this case,
the Actual Work (and Work) fields change to 64 hours?!?!?
Can someone shed some light on what is going on here? I can understand the
Duration value changing when I reset the Actual Finish date, but why is the
Actual Work value changing? And in the first case, why doesn't Work change
to match Actual Work when the task is "closed" by setting the Actual Finish
date? In my mind, the Actual fields should be immutable with the exception
of the Start-Finish-Duration relationship.