J
JaneH
I have to finish a project on a certain date but I schedule the project from
a start date as I want all tasks to start As Soon As Possible. I use a Finsh
No Later Than constraint on a milestone task at the end of the project to
forewarn me (when I update my project plan with actual information) if the
project is likely to finish late. I can then add resources to tasks to bring
the project back on track. Up until now this has worked very well for me.
On my current project however, I need to finish the project by 29th May 2009
and so have have set my FNLT constraint for that date, and one of my tasks
has delayed the project so that it is scheduled to finish on 27th May 2009.
I am still getting the planning wizard box up telling me that there is a
scheduling conflict. This is the only constraint I have set. Any ideas what
I may have done and where that may be causing this
a start date as I want all tasks to start As Soon As Possible. I use a Finsh
No Later Than constraint on a milestone task at the end of the project to
forewarn me (when I update my project plan with actual information) if the
project is likely to finish late. I can then add resources to tasks to bring
the project back on track. Up until now this has worked very well for me.
On my current project however, I need to finish the project by 29th May 2009
and so have have set my FNLT constraint for that date, and one of my tasks
has delayed the project so that it is scheduled to finish on 27th May 2009.
I am still getting the planning wizard box up telling me that there is a
scheduling conflict. This is the only constraint I have set. Any ideas what
I may have done and where that may be causing this