M
Miaplacidus
Project plans according to calendar months. We use COBRA for some of our
reporting requirements, but COBRA is set up on fiscal months.
So, I may have 160 hours scheduled for August in Project, but in COBRA
August is defined as July 30 to Aug 26.
My task is to get the hours accurately converted from the project plan to
COBRA. My initial response is WTH: let August be August and put 140 hours in
COBRA and be done with it. Apparently some people believe this will raise
havoc when it comes to variance reports.
Anybody had similar experience?
Can I create a COBRA like calendar for Project, somehow?
Failing that, I suppose I have to create a lookup table in Excel or
something, and write some code to do a day by day transfer, by task and
resource. BARF.
reporting requirements, but COBRA is set up on fiscal months.
So, I may have 160 hours scheduled for August in Project, but in COBRA
August is defined as July 30 to Aug 26.
My task is to get the hours accurately converted from the project plan to
COBRA. My initial response is WTH: let August be August and put 140 hours in
COBRA and be done with it. Apparently some people believe this will raise
havoc when it comes to variance reports.
Anybody had similar experience?
Can I create a COBRA like calendar for Project, somehow?
Failing that, I suppose I have to create a lookup table in Excel or
something, and write some code to do a day by day transfer, by task and
resource. BARF.