helene;4134423 said:
i have a problem with the fiscal year calendar of the timescale - gantt
chart
- which does display 53 weeks instead of 52. as a result week 01 is the
one
of 5th january while according to any calendars, 5th january belongs to
week
02 2009. is there a way this can be changed? this is leading to lots
of
confusions and incorrect data with regards to timing and deadlines.
Many
thanks in advance
There is half a solution:
Provided (1) your project plan is less than 1 year long and (2) your
project will finish on or before the last day of the last calendar week
in the year then we can use MS Project options to display the correct CW
for 2009 as follows:
Menu -Project
roject Information- - set "Project Start Date" to the
first day of the first week in your calendar year. For 2009, assuming
you have "Week starts on" set to "Sunday" in menu
-Tools:Options:Calendar- then set "Project Start Date" to 28 December
2008
In the Gantt Chart Timescale panel set -Units- to "Week" and -Label- to
"W1, W2, W3, W4......(From Start)"
Your week number will now display correctly for 2009 but if your
project runs into 2010 then the week number will continue to count
upwards into 53, 54, 55 etc. Hence the restrictions with this solution
mentioned above.
Finally, you might like to go in to menu -Tools:Options:Schedule- and
set the value against "New Tasks" to "Start on Current Date" to make
adding new tasks easier later in the year.
It's only half a solution because it only works for 1 calendar year at
a time but it might just do the job.