G
greg
Hello,
I have a basic question on the Gantt chart and start and finish dates.
Say I have a task, 16 hours.
In the resource usage view I put the task for 5-11 and 5-12.
But back in the gantt view, lets say the start is 2-23 to 5-12
If I try and put the start to 5-11 then the end goes way out (weeks out).
even though the task would fit in the time.
I have my task set to fixed work. because I want the work to remain 16
hours.
is there a way to shrink the duration to a more compact date range?
thanks
I have a basic question on the Gantt chart and start and finish dates.
Say I have a task, 16 hours.
In the resource usage view I put the task for 5-11 and 5-12.
But back in the gantt view, lets say the start is 2-23 to 5-12
If I try and put the start to 5-11 then the end goes way out (weeks out).
even though the task would fit in the time.
I have my task set to fixed work. because I want the work to remain 16
hours.
is there a way to shrink the duration to a more compact date range?
thanks