Hiya,
We use a lot of sub contractors and I'd like to set a fixed cost on some
tasks as opposed to an hourly / daily rate etc.
For example
We pay Mr. X $500 for building a wall no matter if it takes him 2 days or 2
weeks. Is the best way for this to create a material resource of $500 for
the task or can you do this with a people resource?