Fixed cost on tasks

C

Corne

Hiya,

We use a lot of sub contractors and I'd like to set a fixed cost on some
tasks as opposed to an hourly / daily rate etc.

For example
We pay Mr. X $500 for building a wall no matter if it takes him 2 days or 2
weeks. Is the best way for this to create a material resource of $500 for
the task or can you do this with a people resource?
 
J

JulieS

Hi Corne,
If you apply the cost table to the task sheet (View --> Table--> Cost) there
is a Fixed Cost field where you could put your $500.00 for the task. You can
also specify whether the fixed cost accrues at the Start, End, or prorated
through the task duration.

Hope this helps. Let us know how you get along.
Julie
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top