LindaC said:
I am displaying only the Fixed Cost field in the timescaled area. I have the
Fixed Cost Accrual set to Start. I'm showing quarters in the timescale and my
task began on 1/22/07 so the Fixed Cost shows in the 1Q07 column. But if I
change the % complete to anything other than 0%, the Fixed Cost in the 1Q07
column changes to $0, even though the correct amount is still in the
(non-timescaled) Fixed Cost field. When I change % complete back to 0%, the
full Fixed Cost amount again appears in the 1Q07 timescaled column. I don't
have any of the settings checked under Tools - Options - Calculate. I'm
running Project Professional 2002 SP1 but my co-workers are seeing the same
thing with Project 2003 SP2.
LindaC,
The "secret" is the fact that you are not having Project calculate costs
(i.e. Tools/Options/Calculation tab). With that option turned off,
Project will initially show the fixed cost in the timescale data as a
placeholder. However, once you indicate that any progress has occurred
on the task, Project then basically resets and waits for the user to
enter values in the Actual Cost field. As a matter of fact, at that
point it doesn't matter if you have set the fixed cost accrual at start,
prorated or end, the user can enter timescale values for actual cost for
any time period, including those outside the task's scheduled start and
finish dates.
Note that if you display the Cost field in the timescaled data, it will
track the actual cost entries.
I admit, what you are seeing seems a little weird, but that's the way it
works.
John
Project MVP