N
Nathalie
Hi,
I have questions about Fixed costs.
I have several activities with fixed costs.
I update the status date.
If I go to the task usage form,( I add the Actual cost row), I can't modify
the cost that has been divided in the different months of the period and when
I enter values in the actual cost, instead of having the same behaviour as
for the work, the cost sums up the initial value with the actual value.
Do I do something wrong?
thanks
Nathalie
I have questions about Fixed costs.
I have several activities with fixed costs.
I update the status date.
If I go to the task usage form,( I add the Actual cost row), I can't modify
the cost that has been divided in the different months of the period and when
I enter values in the actual cost, instead of having the same behaviour as
for the work, the cost sums up the initial value with the actual value.
Do I do something wrong?
thanks
Nathalie