J
Jon Baldan
Hi
We are curerntly using the EPM solution with MS Project 2003 and Project
Server 2003. We have our project plans in this. Some of our contractor
resources are on a fixed daily rate, regardless of how long they work. Our
defualt working hours is 8hrs. For budgetting purposes, we ensure our
reosurces are levelled but when recording actuals, if a contractor puts in
10hrs, then the result is that an actual cost of Contractor Rate x 10/8 is
given for the value of this work. We don't want our contractors to have to
record an overtime figure for the extra 2 hours and our company policy is to
record actual hours (i.e. recording 8 hrs when you work 10 is not an option).
Any help which people can supply would be appreciated.
Jon
We are curerntly using the EPM solution with MS Project 2003 and Project
Server 2003. We have our project plans in this. Some of our contractor
resources are on a fixed daily rate, regardless of how long they work. Our
defualt working hours is 8hrs. For budgetting purposes, we ensure our
reosurces are levelled but when recording actuals, if a contractor puts in
10hrs, then the result is that an actual cost of Contractor Rate x 10/8 is
given for the value of this work. We don't want our contractors to have to
record an overtime figure for the extra 2 hours and our company policy is to
record actual hours (i.e. recording 8 hrs when you work 10 is not an option).
Any help which people can supply would be appreciated.
Jon