B
BCDS
We are attempting to do resource availablity reporting across an enterprise.
I am using Project 2007 Standard. We send out a template with a standard
resource pool having common tasks. We want regional managers to fill out the
resource assignments on the standard tasks using resources from their pool.
Each task is 1 year long so we are using a duration of 245 working days based
on our standard calendar. All tasks are Fixed Duration and NOT Effort Driven.
We have a task called "Vacation, Training" that is 245 days in duration. We
would like to assign resources to this task but be able to specifically put
in the start and stop dates for each resource. Joe takes a week off in July
and Mary in September. We don't want to put subtasks in for Joe and another
for Mary.
Initialy we tried assigning Joe at 2% (39.2hrs) to be spread across the
entire duration. We then went into the Task Usage view, selected Joe, and
put 8 hrs on the days of July 5-9 for a total of 40. The other days, we
changed to 0hrs. The duration of the task changed to 40 hours (5 days).
This is a fixed duration task so this suprised us.
I am using Project 2007 Standard. We send out a template with a standard
resource pool having common tasks. We want regional managers to fill out the
resource assignments on the standard tasks using resources from their pool.
Each task is 1 year long so we are using a duration of 245 working days based
on our standard calendar. All tasks are Fixed Duration and NOT Effort Driven.
We have a task called "Vacation, Training" that is 245 days in duration. We
would like to assign resources to this task but be able to specifically put
in the start and stop dates for each resource. Joe takes a week off in July
and Mary in September. We don't want to put subtasks in for Joe and another
for Mary.
Initialy we tried assigning Joe at 2% (39.2hrs) to be spread across the
entire duration. We then went into the Task Usage view, selected Joe, and
put 8 hrs on the days of July 5-9 for a total of 40. The other days, we
changed to 0hrs. The duration of the task changed to 40 hours (5 days).
This is a fixed duration task so this suprised us.