S
Steve Lundwall
I set up a Fixed Duration task for two hours. It is a meeting. I assigned
myself at 100% Units and the Work field calculated to 2 hours. Fine. I also
assigned someone else for 100% because they would be there for 2 Hours as
well. I reported back using PWA that I 'worked' it for 2 hours. When I
accept it into the Project it changes the duration of the so called Fixed
Duration task to 3 hours and 30 minutes and it changes my Units to 57% but
leaves my Work at 2H. Huh?
Okay, I give up. How do you set up a Meeting like this without Project
changing your duration? Thanks.
(Is this the 'New Math?)
Steve
myself at 100% Units and the Work field calculated to 2 hours. Fine. I also
assigned someone else for 100% because they would be there for 2 Hours as
well. I reported back using PWA that I 'worked' it for 2 hours. When I
accept it into the Project it changes the duration of the so called Fixed
Duration task to 3 hours and 30 minutes and it changes my Units to 57% but
leaves my Work at 2H. Huh?
Okay, I give up. How do you set up a Meeting like this without Project
changing your duration? Thanks.
(Is this the 'New Math?)
Steve