Fixed Duration task type

D

Donna

Hi -
I''ve created a functional project for my PM team to use as a bucket to put
time against general Program Management items that don't relate to a specific
project - an overhead project. I set these up on a quarterly basis.
Fixed Duration - non-effort driven is the task type.
However - as my team reports against this - the duration time changes and so
does the task type to Fixed Units?
We have SP1 plus the latest hotfixes (working on testing the new ones that
just came out July 15th...)
I've tried to put constraints with a Must Finish to keep the end date from
changing - but it just does.
 