A
Amanda O
Help!
I have a fixed duration task. When I enter "Work" (planned hours), I
receive a message that the resource cannot complete the task within the
duration and it adjusts the end date way into the future.
As I continue reducing the duration and re-entering the work to force the
scheduling, it continues to move the finish date further and further into the
future.
I have a fixed duration task. When I enter "Work" (planned hours), I
receive a message that the resource cannot complete the task within the
duration and it adjusts the end date way into the future.
As I continue reducing the duration and re-entering the work to force the
scheduling, it continues to move the finish date further and further into the
future.