C
Craig Kalugin
I have been using Project 2003 for several years now. All of a sudden i have
a weird and dangerous problem. When i add tasks to my project, i always used
fixed duration (Not Effort Driven). The tasks duration never changes unless i
change it. Now all of a sudden i have tasks (not all) changing duration
whenever i do a "Level Resources". Keep in mind i use a project with many
subprojects. Has anyone seen this before. Is something corrupted? I thought
durations are not supposed to change? Please help. As of now my huge project
is useless.
a weird and dangerous problem. When i add tasks to my project, i always used
fixed duration (Not Effort Driven). The tasks duration never changes unless i
change it. Now all of a sudden i have tasks (not all) changing duration
whenever i do a "Level Resources". Keep in mind i use a project with many
subprojects. Has anyone seen this before. Is something corrupted? I thought
durations are not supposed to change? Please help. As of now my huge project
is useless.