S
Sharon AZ
I have a group of tasks that can be completed in any order
within a given time period however they all need to be
completed by a given date. They all link to a subsequent
task that can't begin until all the these previous tasks
are completed. These tasks are completed by a group
outside of our own so I'm only interested in tracking the
percent complete of each task to ensure they are done by
the given finish date. What is the best way to set up
these group of tasks? Right now I'm having a problem with
the tasks splitting whenever I enter a percent complete
amount.
Thank You
Sharon
within a given time period however they all need to be
completed by a given date. They all link to a subsequent
task that can't begin until all the these previous tasks
are completed. These tasks are completed by a group
outside of our own so I'm only interested in tracking the
percent complete of each task to ensure they are done by
the given finish date. What is the best way to set up
these group of tasks? Right now I'm having a problem with
the tasks splitting whenever I enter a percent complete
amount.
Thank You
Sharon