J
John
I am attempting to setup a training schedule and assign instructional
resources into Project. The training schedule is based on an 8 hour day and
I have a pool of instructors I'm using to teach. When I add resources,
Project adjusts some of my teaching times for future dates and eventually
throws off the set teaching schedule. I've attempted to Fix duration and turn
off effort driven but that doesn't seem to work. Any ideas on whether its a
calendar issue between my resources and project schedule or do I have the
wrong fixed type.
Thanks
resources into Project. The training schedule is based on an 8 hour day and
I have a pool of instructors I'm using to teach. When I add resources,
Project adjusts some of my teaching times for future dates and eventually
throws off the set teaching schedule. I've attempted to Fix duration and turn
off effort driven but that doesn't seem to work. Any ideas on whether its a
calendar issue between my resources and project schedule or do I have the
wrong fixed type.
Thanks