R
reb-clo
Hi
I am working with a project manager who says he was advised to create a set
of tasks as fixed work tasks. However, these are bucket tasks so we are not
able to accurately estimate how much work they require.
I suggested to him that he uses fixed duration instead. Would this work? he
said that he was told not to use thit task type, but I don't know why.
Would changing it to fixed duration now upset anything, as protected actuals
have been booked against these tasks.
Thanks!
I am working with a project manager who says he was advised to create a set
of tasks as fixed work tasks. However, these are bucket tasks so we are not
able to accurately estimate how much work they require.
I suggested to him that he uses fixed duration instead. Would this work? he
said that he was told not to use thit task type, but I don't know why.
Would changing it to fixed duration now upset anything, as protected actuals
have been booked against these tasks.
Thanks!