I have seen a lot of questions about fixed duration but I don't see a final
resolution. This is our situation:
1 - SP2 installed on the clients, whatever the server version before SP2A on
the server
2 - We use managed time frames
3 - Fixed duration tasks, with effort driven off, no constraints. These are
production type tasks so the durations go from 2/6/06 through 3/30/07
4 - We use an enterprise resource calendar so no Project Managers have the
ability to block out a plan resource calendar
5 - When time is recorded in PWA, we will see the durations change - the
time is recorded in May so we aren't anywhere near the completion date. This
is a sporadic problem and we can't figure this out.
Any ideas?
PK Consulting
resolution. This is our situation:
1 - SP2 installed on the clients, whatever the server version before SP2A on
the server
2 - We use managed time frames
3 - Fixed duration tasks, with effort driven off, no constraints. These are
production type tasks so the durations go from 2/6/06 through 3/30/07
4 - We use an enterprise resource calendar so no Project Managers have the
ability to block out a plan resource calendar
5 - When time is recorded in PWA, we will see the durations change - the
time is recorded in May so we aren't anywhere near the completion date. This
is a sporadic problem and we can't figure this out.
Any ideas?