Fixed Duration?

A

anovak

I've got folks who wish to track time they spend during, say a 2 week
period, when they are communicating with a vendor that has a task in
their court. From what I see of how Fixed Duration works, its best
not to go that route and just have a 0 hour task that you assign
yourself to. Comments?
 
P

Projectability

You could set the task type to Fixed Units not Effort driven, this will
allow you to allocate a defined amount of work to each person assigned to
the task and Project will calculate the % allocation for each person without
impacting on the duration - it will then show the assigned work spread
evenly over the duration (flat work contour).

--
Dominic Moss

Projectability - Helping People achieve more with Microsoft Project

Check the Downloads section on our Website for useful documents on both
Project Management and Microsoft Project

www.projectability.co.uk

Why not subscribe to our monthly newsletter for hints tips and views

http://visitor.constantcontact.com/manage/optin/ea?v=001WVdpo956d6lHqIISFtfgVw==
 