Doug Huston
I want to use Project as a tool to set-up a 24 hours
Schedule of production jobs run each day by Operations. I
need to have the durations IN MINUTES at Fixed Starting
Times, and most importantly, I need the Bar to visually
appear showing the times on the Bar Chart.
When I type-in the Start time and manually type-in the
minutes into the Duration field, the Bar disappears.
How do I set a Fixed Starting Time, type-in the minutes,
and all the while having the Bar appear on the Bar Chart
(which is set-up on 30 minute intervals during a 24 hour
day.)
I am a relatively new User of MSProject, so I have a huge
learning curve to overcome.
I sincerely appreciate any help you can provide. I have
to have all jobs run by Operations on a Schedule this week
and need to have the duration times reflected in the Bar
Chart as a good visual.
Thank you very much.
Doug
616-866-5583
Schedule of production jobs run each day by Operations. I
need to have the durations IN MINUTES at Fixed Starting
Times, and most importantly, I need the Bar to visually
appear showing the times on the Bar Chart.
When I type-in the Start time and manually type-in the
minutes into the Duration field, the Bar disappears.
How do I set a Fixed Starting Time, type-in the minutes,
and all the while having the Bar appear on the Bar Chart
(which is set-up on 30 minute intervals during a 24 hour
day.)
I am a relatively new User of MSProject, so I have a huge
learning curve to overcome.
I sincerely appreciate any help you can provide. I have
to have all jobs run by Operations on a Schedule this week
and need to have the duration times reflected in the Bar
Chart as a good visual.
Thank you very much.
Doug
616-866-5583