G
Gil
Hi all,
In order to create a "project management task", which lasts as long as
the project lasts, I followed advice from this group, and have created
a hammock task, fixed units, not effort driven, and assigned it to the
PM with 50% units, and got the desired result: the task is scheduled
4 hours a day, for the length of the project.
The problem begins when actual work values are entered.
If on a given day the project manager enter 6 hours of actual work,
instead of the planned 4, project automatically change the planned
work for the day after from 4 to 2, trying to keep total work for the
assignment as it was.
The result I am trying to accomplish is this: No matter what is the
actual value that them PM enters, the (planned) work for the following
days won't change (in my example, I want it to stay 4,4,4,4…).
I have tried all task types, none is doing what I need.
Any help or thoughts will be appreciated!
Thanks,
Gil
In order to create a "project management task", which lasts as long as
the project lasts, I followed advice from this group, and have created
a hammock task, fixed units, not effort driven, and assigned it to the
PM with 50% units, and got the desired result: the task is scheduled
4 hours a day, for the length of the project.
The problem begins when actual work values are entered.
If on a given day the project manager enter 6 hours of actual work,
instead of the planned 4, project automatically change the planned
work for the day after from 4 to 2, trying to keep total work for the
assignment as it was.
The result I am trying to accomplish is this: No matter what is the
actual value that them PM enters, the (planned) work for the following
days won't change (in my example, I want it to stay 4,4,4,4…).
I have tried all task types, none is doing what I need.
Any help or thoughts will be appreciated!
Thanks,
Gil