J
Joy
we have to replace Actual Work and Remaining Work with some values.
do we have to set Default task type to be "fixed work"??
we used fixed unites, and sometimes, after copying, the values in Actual and
Remaining Work are not exactly the same as what we like them to be.
like
if we use fixed units
we have values 0.2, 0.5, copy them to Act and Rem Work respectively.
before that, We have a task: Duration: 2, %complete: 0%, Act: 0, Rem: 2
then when we copy 0.5 to Rem first
then we copy 0.2 to Act,
at the time, Act is changed to 0.2, but Rem is changed to 0.3. -- not what
we want
if we copy 0.2 to Act first,Rem is automatically set to 1.8
then, we copy 1.8 to Rem, we get Act: 0.2,Rem: 0.5, which is what we want.
thanks
do we have to set Default task type to be "fixed work"??
we used fixed unites, and sometimes, after copying, the values in Actual and
Remaining Work are not exactly the same as what we like them to be.
like
if we use fixed units
we have values 0.2, 0.5, copy them to Act and Rem Work respectively.
before that, We have a task: Duration: 2, %complete: 0%, Act: 0, Rem: 2
then when we copy 0.5 to Rem first
then we copy 0.2 to Act,
at the time, Act is changed to 0.2, but Rem is changed to 0.3. -- not what
we want
if we copy 0.2 to Act first,Rem is automatically set to 1.8
then, we copy 1.8 to Rem, we get Act: 0.2,Rem: 0.5, which is what we want.
thanks