B
Babar
I have a fixed unit task with effort driven checked in a project. When
I assign more than 1 resource to it, the duration doesn't recalculate.
Even if I try the same thing on a new project on my computer, the
duration doesn't change .. weird.
I think it might be do with some setting but I'm not completely sure.
Any help would be greatly appreciated.
Babar
I assign more than 1 resource to it, the duration doesn't recalculate.
Even if I try the same thing on a new project on my computer, the
duration doesn't change .. weird.
I think it might be do with some setting but I'm not completely sure.
Any help would be greatly appreciated.
Babar