T
Terri
Using MSP 2007
I was added to a project that is in the proposal stage and took over an
existing schedule.
The original scheduler had it as fixed units, and did a preliminary resource
loading. Now the estimates have changed and I need to adjust the hours. I
want it to be fixed work and let the duration calculate based on amount of
work. I did change all the task types to fixed work and then started
adjusting the hours.
My question, (I may not even have to worry about it, but it is bugging me)
is when I adjust the hours on a resource using the gant chart view, split
window, task details form on bottom split, the units are adjusting for some
resources, but for some it is staying at whatever the unit percentage was
there prior to the adjustment or is changing to 100% for less that 100% effot.
Example:
Total work for the activity is 120 hours split over 3 resources 100 hours
for 1 and 10 hours each for the other 2.
The 100 hours is giving me 12.5 day duration, since this is engineering, I
am allowing some float so I adjust the duration to 15 days. This reduced the
units for the 100 hours correctly to 83% the other two are staying at 100%
which I would have expected to see 8% on. Is there an explanation why some
units adjust correctly while other stay where they were prior to the
adjustments?
Thanks in advance for any help.
I was added to a project that is in the proposal stage and took over an
existing schedule.
The original scheduler had it as fixed units, and did a preliminary resource
loading. Now the estimates have changed and I need to adjust the hours. I
want it to be fixed work and let the duration calculate based on amount of
work. I did change all the task types to fixed work and then started
adjusting the hours.
My question, (I may not even have to worry about it, but it is bugging me)
is when I adjust the hours on a resource using the gant chart view, split
window, task details form on bottom split, the units are adjusting for some
resources, but for some it is staying at whatever the unit percentage was
there prior to the adjustment or is changing to 100% for less that 100% effot.
Example:
Total work for the activity is 120 hours split over 3 resources 100 hours
for 1 and 10 hours each for the other 2.
The 100 hours is giving me 12.5 day duration, since this is engineering, I
am allowing some float so I adjust the duration to 15 days. This reduced the
units for the 100 hours correctly to 83% the other two are staying at 100%
which I would have expected to see 8% on. Is there an explanation why some
units adjust correctly while other stay where they were prior to the
adjustments?
Thanks in advance for any help.