K
Ken Z
Project 2003, SP2 question:
I set up a task of fixed work. Work is set at 40 hours. I enter Resource A
at 50%, Project figures out it will take two weeks at 4hrs a day and sets the
duration to 10d. All is good.
I then enter Actual Work for Resource A. Let's say A works only 2 hours on
the first day instead of the alloted 4 hrs. Project then calculates out that
Resource A will need to work those other two hours on day 11.
Is there anyway to tell Project to leave the duration at 10 and increment
the units, at least until a resource hits 100% units. I guess the same holds
going the opposite way. If a resource works 8 hours instead of 4, rather than
pulling in the duration by a day, I'd rather Project change the units from
50% to 40% (or whatever the correct calculation would be to keep work at 40
hrs and duration at 10 days.
Thanks in advance for the help.
I set up a task of fixed work. Work is set at 40 hours. I enter Resource A
at 50%, Project figures out it will take two weeks at 4hrs a day and sets the
duration to 10d. All is good.
I then enter Actual Work for Resource A. Let's say A works only 2 hours on
the first day instead of the alloted 4 hrs. Project then calculates out that
Resource A will need to work those other two hours on day 11.
Is there anyway to tell Project to leave the duration at 10 and increment
the units, at least until a resource hits 100% units. I guess the same holds
going the opposite way. If a resource works 8 hours instead of 4, rather than
pulling in the duration by a day, I'd rather Project change the units from
50% to 40% (or whatever the correct calculation would be to keep work at 40
hrs and duration at 10 days.
Thanks in advance for the help.