Hello Cadilly,
I assume you are looking at the Detail Gantt view. To show Slack
(Microsoft term for Float) for all tasks except summary, choose
Format > Bar Styles. Find the bar style for "Slack" and add "Not
Summary" (without the quote) to the "Show for" section.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project