C
Carl Gibson
I have 3 tasks - A,B, and C.
The duration of Task B should not be fixed. Instead, I
would like Task B to begin when Task A begins. Also, I
would like Task B to end when Task C ends. I have
specified hard dates for Tasks A (start) & C (end).
If I change the start date of Task A or the end of Task C,
I would like to Task B to adjust its duration
automatically.
For Task B, I have set Predecessors to the following:
Task A - Finish to Start
Task C - Finish to Finish
Unfortunately, Task B will not adjust its duration. It
will honor its predecessor constraint to Task A, but not
Task C.
How do I make the duration of Task B adjust automatically?
Thanks.
The duration of Task B should not be fixed. Instead, I
would like Task B to begin when Task A begins. Also, I
would like Task B to end when Task C ends. I have
specified hard dates for Tasks A (start) & C (end).
If I change the start date of Task A or the end of Task C,
I would like to Task B to adjust its duration
automatically.
For Task B, I have set Predecessors to the following:
Task A - Finish to Start
Task C - Finish to Finish
Unfortunately, Task B will not adjust its duration. It
will honor its predecessor constraint to Task A, but not
Task C.
How do I make the duration of Task B adjust automatically?
Thanks.