M
Michael.Tarnowski
Hi
I have to set up a schedule in MSP where some dates are already
contractually agreed with customer and sub-cos and the tasks have to
be planned backward in line with these cornerstones.
For this I setup on top of the task list all contractually agreed
dates as milestones, for brevity sake I call them "external dates".
In the schedule I dispersed "internal" milestones on certain stages/
events when progress or a work product is achieved. All tasks are ALAP
and FS linked ones.
Now the idea: I want to link the start / end date of an external
deadline to it's counterpart inside the schedule, thus when shifting
the external one, the internal shifts as well and all tasks are
rescheduled in line with the new constraint.
On the other hand when an internal deadline is achieved earlier than
the external states, the external should not be affected (we have a
great slack).
Now my questions:
a) should I put the deadline dates in the Deadline field of the
external milestones?
b) should I use an OLE-linkage between start/end dates of external and
internal milestones or an MSO/MFO constraint?
c) I read by Eric Uyttewaal that each task should have at least one
predecessor and one successor; Jim Aksel wrote here in one post,
milestones should have either a predecessor OR one successor, but not
both. - Should I specify for the internal milestones successors since
they are gates for proceeding to the next stage/phase?
What will give me the most flexible schedule?
Thanks for your answers & have a nice day
Michael
I have to set up a schedule in MSP where some dates are already
contractually agreed with customer and sub-cos and the tasks have to
be planned backward in line with these cornerstones.
For this I setup on top of the task list all contractually agreed
dates as milestones, for brevity sake I call them "external dates".
In the schedule I dispersed "internal" milestones on certain stages/
events when progress or a work product is achieved. All tasks are ALAP
and FS linked ones.
Now the idea: I want to link the start / end date of an external
deadline to it's counterpart inside the schedule, thus when shifting
the external one, the internal shifts as well and all tasks are
rescheduled in line with the new constraint.
On the other hand when an internal deadline is achieved earlier than
the external states, the external should not be affected (we have a
great slack).
Now my questions:
a) should I put the deadline dates in the Deadline field of the
external milestones?
b) should I use an OLE-linkage between start/end dates of external and
internal milestones or an MSO/MFO constraint?
c) I read by Eric Uyttewaal that each task should have at least one
predecessor and one successor; Jim Aksel wrote here in one post,
milestones should have either a predecessor OR one successor, but not
both. - Should I specify for the internal milestones successors since
they are gates for proceeding to the next stage/phase?
What will give me the most flexible schedule?
Thanks for your answers & have a nice day
Michael