Hi,
The reason why Project isn't nice to you is because it tries to scheduel
taskks when they become possible. Things like forcing tasks to enter
together with other tasks simply isn't there, ast least if you cannot fix
that date.
I am somehow curious though, why force taska to end together? I fail to see
a reason for that (Project or not project). If one of the task finishes
early, how bad is that? what is the penalty?
More, is there one of the tasks that can be considered "leading", i.e.
setting the end dates for the other tasks?
If yes, there is a (very unelegant but still) solution:
Copy the finish date of the "leading" task (Edit, Copy)
Paste Special, Paste Link in the finish field of the other tasks.
But I still wonder why, with somebody workking faster tahn expected, he
can't finish a day early
Greetings,
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
To clarify, I don't need them to be done on a specific day, I need
them to be done on the same day (all four on the same day). I want MS
Project to determine the best day when all the resources (people) are
available at the same time, when all the predecessor tasks assigned to
the individuals are complete, and the resources for all tasks are
received. Since the three people only work part-time, it is helpful
to have MS Project determine this for me.
Specifically, this is moving day for a group in an area of the office
and we would like to have it done in one day. One person looks after
moving computers and power, two people are needed to box up/unbox
their desk and assist with the move, and another is helping with the
heavy lifting. Some tasks are to acquire new furniture and prepare
the office. When is the best day for the move based on availability
and predecessor tasks of the individuals and other physical resources?
Thanks for your help,
Michele
P.S. - I'm still on Project 2003. I hope that 2007 is better because
I find 2003 awkward and often of need of manual intervention which, in
my opinion, is the point of the software - here are the tasks, here
are the constrains, set me a schedule.