Force to show 'Hour' unit in Work and Remaining Work fields in the MYTasks view from server

T

TH

Hi,
Is there any way I can set the default unit to 'Hours' for Work and
Remaining Work fields in the 'My Tasks' view from the server settings
so that all uses see the 'Hour' unit instead of 'Day'? I know that
individual users can change this setting in the web parts but I would
like do it from the server for all PWA users.
 
M

Marc Soester [MVP]

within the PWA page under My task, you can change the web part value, this
should apply to all users. Can you please apply hours to the my task site,
that should do the trick.
Thanks
 
T

TH

within the PWA page under My task, you can change the web part value, this
should apply to all users. Can you please apply hours to the my task site,
that should do the trick.
Thanks
--
Marc Soester [MVP]
National Manager: EPMhttp://marcsoester.blogspot.com





- Show quoted text -

Hi Mrac,
I've tried and it worked fine. Thanks.

TH
 