Forcing calculated end-date on milestones

J

j_chp

Hello everyone,

In our company (using EPM) we use specific task-texts for several
milestones (that are present in most of the projects). These milestones

are linked to each other most of the time. The last milestone occurs on

the last Thursday each month. Is it possible to use a formula that -
when it finds a certain string in the task-name - forces that task to
occur on the right date (maybe using a specific task-calendar)? If this

would be possible, a delay in for example the first milestone, would
result in the last milestone shifting to the next month
(automatically).


I hope I've described my problem well enough for you to figure out a
solution!
 
G

Gary L. Chefetz [MVP]

Apply a task calendar to the milestone that only has the last Thursday of
the month a working time.
 