Forecast under-allocated resources

S

Sandy

Is it possible to look ahead 4 wks to see which resources
are "under-allocated"? I'm new to project and can't seem
to figure out if it is a filter issue or what.

Thanks for your help.

sandy
 
J

JulieS

Hi Sandy,
You may wish to take a look at the Resource Usage View.
It gives a timescaled view of when your resources are
working.
You may add the remaining availability to the timescaled
portion (right side) of the view to narrow down how many
hours that resource is available on that day.
 
S

Sandy

Thank you. I'll try that.

sandy
-----Original Message-----
Hi Sandy,
You may wish to take a look at the Resource Usage View.
It gives a timescaled view of when your resources are
working.
You may add the remaining availability to the timescaled
portion (right side) of the view to narrow down how many
hours that resource is available on that day.

.
 