M
maryann
I have a task whose Planned finish date is 7/15/04. As of
7/22, the task is marked as 75% complete. Is there a way
to see what the projected finish date of the task, and the
overall project is, assuming that there are dependant
tasks to this task?
I know that once I add the "Actual Finish Date" into the
task information, thereby making the task 100% complete,
dependant tasks will move out accordingly. What I am
looking for, however, is a view/report to estimate what
the projected Task and/or Project Finish date would be by
calculating the partial completion of overdue tasks.
Any ideas would be greatly appreciated.
thanks
7/22, the task is marked as 75% complete. Is there a way
to see what the projected finish date of the task, and the
overall project is, assuming that there are dependant
tasks to this task?
I know that once I add the "Actual Finish Date" into the
task information, thereby making the task 100% complete,
dependant tasks will move out accordingly. What I am
looking for, however, is a view/report to estimate what
the projected Task and/or Project Finish date would be by
calculating the partial completion of overdue tasks.
Any ideas would be greatly appreciated.
thanks