O
Omar
I currently using MS Project 2003 to manage a Master Schedule (w/ multiple
project schedules) that has seen several schedule slips by multilple vendors.
Due to the nature of the tasking, the schedule is only partially resource
loaded and some customization has been made in terms of fields being tracked.
Can Project provide a snapshot or forecast (no more than 3 months out) of
where the tasking piles up? Essentially I need to be able to provide the
client with a "best guess" of where we could potentially be resource
constrained based on the schedule slips.
project schedules) that has seen several schedule slips by multilple vendors.
Due to the nature of the tasking, the schedule is only partially resource
loaded and some customization has been made in terms of fields being tracked.
Can Project provide a snapshot or forecast (no more than 3 months out) of
where the tasking piles up? Essentially I need to be able to provide the
client with a "best guess" of where we could potentially be resource
constrained based on the schedule slips.