Format of the dates

¿

¿?

Hi,
On the email that a resource receive informing that a task
has been assigned I would like to change the format of the
date.
Change it from the format of Month/Day/Year to the
European way of Day/Month/Year.
Thanks,


Task Name: XXX
Start: 1/19/04 Finish: 2/9/04 Work: 12.6h Rem
Work: 12.6h
 
M

Mike Glen

Hi ?,

Welcome to this Microsoft Project newsgroup :)

Thes are basic formats that are taken from the way Windows is set up on the
user's PC. Change them through the Control Panel/International settings.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 