I've follwed the directions in the FAQ 31 ---

I've made the customized flag. Got the Bars formatted -- but when I put the
projects in the Combined Project.... I'm still not getting the correctly
formatted fields.

Do I have to create a column for each of the flag fields in th combined
project? And another column for each customized field?
 
A

Andrew Lavinsky

Did you change the views in the subproject and then insert it into the master
project? Or did you change the views in the master project, which then had
subprojects inserted?

That latter should work, not the former.

-A


- Andrew Lavinsky
Blog: http://blogs.catapultsystems.com/epm
 
J

John

Muli-Project Projector <Muli-Project
I've follwed the directions in the FAQ 31 ---

I've made the customized flag. Got the Bars formatted -- but when I put the
projects in the Combined Project.... I'm still not getting the correctly
formatted fields.

Do I have to create a column for each of the flag fields in th combined
project? And another column for each customized field?

Multi-Project,
Just a little expansion on what Andrew said. With regard to views and
formatting, a master file and it's inserted subprojects are independent.
In other words, a custom formatted Gantt Chart view in a subproject will
not show up as a customized formatted view in the master and vice versa.
Each file must be separately formatted.

Hope this helps.

John
Project MVP
 
R

Rod Gill

Or,

Copy the New View to the Global.mpt file using the Organizer (Tools menu).
Everything in the Global.mpt file is available to all your projects.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com




John said:
Muli-Project Projector <Muli-Project


Multi-Project,
Just a little expansion on what Andrew said. With regard to views and
formatting, a master file and it's inserted subprojects are independent.
In other words, a custom formatted Gantt Chart view in a subproject will
not show up as a customized formatted view in the master and vice versa.
Each file must be separately formatted.

Hope this helps.

John
Project MVP

__________ Information from ESET Smart Security, version of virus
signature database 4582 (20091107) __________

The message was checked by ESET Smart Security.

http://www.eset.com

__________ Information from ESET Smart Security, version of virus signature database 4582 (20091107) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top