I have a consolidated project file that requires some formatting. It has 7
projects inserted. A request has been made to color code the tasks, including
summary tasks, based on project. When I did that I came upon a limit on the
number cells you can directly format (aproximatley 64000). My view has only 4
columns and about 7000 tasks. Is there a way around this. I am working with
Project professional.
projects inserted. A request has been made to color code the tasks, including
summary tasks, based on project. When I did that I came upon a limit on the
number cells you can directly format (aproximatley 64000). My view has only 4
columns and about 7000 tasks. Is there a way around this. I am working with
Project professional.