Steve Scott
I want to quick RAG rate some milestones across 30 different plans that I
have inserted into a Master plan for this purpose. Must the formula I want
eg comparing Baseline Finish versus Finish be embedded in the sub-projects or
can I do this just in the Master Project ?
Also could someone remind me how I aggregate RAG values to summary level and
all the way upto the Project Summary Task?
have inserted into a Master plan for this purpose. Must the formula I want
eg comparing Baseline Finish versus Finish be embedded in the sub-projects or
can I do this just in the Master Project ?
Also could someone remind me how I aggregate RAG values to summary level and
all the way upto the Project Summary Task?