M
Mark E. Read
This is Project Pro 2007 with SP1 and several hotfixes (with Project
Server), but NOT the infrastructure update yet.
The field is an enterprise task field, but my validation is ALL in
Project Pro. It doesn't work as expected in the Project Pro client.
I have a formula that returns useful information: slippage = finish
variance/baseline duration, and it behaves the way I think it should.
If I have a negative variance, it gives me a negative result.
I then add on graphical indicators with the following order:
slippage equals #error = blank
slippage less than or equal to 0 = green
slippage greater than 0.2 = red
slippage less than 0.2 = yellow.
I set up 4 tasks of 10 days and baseline them.
I display the slippage column and it all glows green. Excellent
I change task 1 duration to 11 days and it goes yellow. Excellent
I change task 2 duration to 12 days and it goes red. Excellent
I remove the baseline from task 3 and it goes blank. Excellent
all good.
Now I change the duration of task 4 to 8 days, and it goes yellow.
WAIT! it's supposed to be green. The FIRST test is less than or
equal to zero. Why doesn't that test work?
I've recreated the field, I've deleted cache and profile and EGT...
still NOTHING.
Any thoughts? Anyone else care to try?
Thanks for your help!
Server), but NOT the infrastructure update yet.
The field is an enterprise task field, but my validation is ALL in
Project Pro. It doesn't work as expected in the Project Pro client.
I have a formula that returns useful information: slippage = finish
variance/baseline duration, and it behaves the way I think it should.
If I have a negative variance, it gives me a negative result.
I then add on graphical indicators with the following order:
slippage equals #error = blank
slippage less than or equal to 0 = green
slippage greater than 0.2 = red
slippage less than 0.2 = yellow.
I set up 4 tasks of 10 days and baseline them.
I display the slippage column and it all glows green. Excellent
I change task 1 duration to 11 days and it goes yellow. Excellent
I change task 2 duration to 12 days and it goes red. Excellent
I remove the baseline from task 3 and it goes blank. Excellent
all good.
Now I change the duration of task 4 to 8 days, and it goes yellow.
WAIT! it's supposed to be green. The FIRST test is less than or
equal to zero. Why doesn't that test work?
I've recreated the field, I've deleted cache and profile and EGT...
still NOTHING.
Any thoughts? Anyone else care to try?
Thanks for your help!