B
bart c
Can i write a formula that shows the number of working days, counting from
the project start date (not each tasks start date!) until each task's finish
date? (So: take the finish date of each task, subtract the start date of the
project (not of the task!) and count how many working days there are in that
range?)
(I don't wont to use the calendar option that counts working days in the
tiers, but the tiers have to show the classical units)
Any suggestions?
the project start date (not each tasks start date!) until each task's finish
date? (So: take the finish date of each task, subtract the start date of the
project (not of the task!) and count how many working days there are in that
range?)
(I don't wont to use the calendar option that counts working days in the
tiers, but the tiers have to show the classical units)
Any suggestions?