B
bitsnpieces
I am setting up a header row in a vacation schedule. It will look
something like this (for Jan and Feb 2003)
|
X 6 13 20 27 | X 3 10 17 24
|
Each of the above signifies the date of the Mondays occurring in
January and February of this year. I entered them manually. The |
bar shows the split between months and I have allotted five weeks for
each month, hence the X when there is no Monday for that particular
calendar week.
Is there a formula I can use, say at the beginning of the row, which
will automatically calculate these dates for me along the entire line
for the entire year?
I've seen and used one before but I don't recall what the formula is.
I think it was set up to calculate every seven days but I don't know
the part of the formula that handled the number of days in each month.
something like this (for Jan and Feb 2003)
|
X 6 13 20 27 | X 3 10 17 24
|
Each of the above signifies the date of the Mondays occurring in
January and February of this year. I entered them manually. The |
bar shows the split between months and I have allotted five weeks for
each month, hence the X when there is no Monday for that particular
calendar week.
Is there a formula I can use, say at the beginning of the row, which
will automatically calculate these dates for me along the entire line
for the entire year?
I've seen and used one before but I don't recall what the formula is.
I think it was set up to calculate every seven days but I don't know
the part of the formula that handled the number of days in each month.