I need to create a formula that populates a custom field called "Task
Summary". What this formula needs to do is populate the "Task Summary" field
with the name of the Summary task for the corresponding Sub task. I do not
know how to go about setting up this formula. Any help is appreciated.

This will function similarly to how the Project field works when in a Master
project.

I am using MOPS 2007, MS Project 2007.

Thanks,
Jennifer
 
J

JulieS

Hello Jennifer L,

You won't be able to accomplish what you seek through a formula
however, you can accomplish what you need through a VBA macro. Jack
Dahlgren has a macro that populates a spare Task Text field with the
name of parent task. You can find Jack's macro page at:
http://masamiki.com/project/macros.htm

See his "Summary Task" macro. If you have follow-up questions about
the macro or modifying the macro, please post to the Developer
newsgroup.


I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
J

Jennifer L

Julie, Thank you so much! I had a feeling it would need to be done in a
macro. Thanks for confirming it. Glad to see there's already one out there.
I'll check out Jack's macro and hopefully implement it into my field.

Thanks again!
Jennifer
 
J

Jennifer L

Just to follow up - I tweaked the macro and it works perfectly! Thanks so
much!!
 
J

JulieS

Superb Jennifer. So glad Jack's macro suited your needs with just a
minor tweak.
Julie
 