P
Pik
I have the data mentioned below - two projects in a program, shared
resources across the projects.
Project Resource Week 1 Week 2 Week 3
-------- -------- ----------------------
Project 1 A 20 20 20
B 10 10 10
Project Resource Week 1 Week 2 Week 3
-------- -------- ----------------------
Project 2 B 25 20 10
C 40 40 40
I need to create a simple resource allocation summary, as shown below.
Resource Allocation Summary
Week 1 Week 2 Week 3
A 20 20 20
B 35 30 20
C 40 40 40
Basically, in the resource allocation summary section, I need (with
value 35 as an example), "Find resource B in Week 1 column of Project
1 and Project 2, and sum the hours spent".
Please help me out. Thanks.
resources across the projects.
Project Resource Week 1 Week 2 Week 3
-------- -------- ----------------------
Project 1 A 20 20 20
B 10 10 10
Project Resource Week 1 Week 2 Week 3
-------- -------- ----------------------
Project 2 B 25 20 10
C 40 40 40
I need to create a simple resource allocation summary, as shown below.
Resource Allocation Summary
Week 1 Week 2 Week 3
A 20 20 20
B 35 30 20
C 40 40 40
Basically, in the resource allocation summary section, I need (with
value 35 as an example), "Find resource B in Week 1 column of Project
1 and Project 2, and sum the hours spent".
Please help me out. Thanks.