W
Wendy
I am having problems with some formula.
My task level custom date fields stop working when they become summary
tasks. Here is teh formula: IIf([Name]="PHASE 4-SITE SEARCH
PROCESS",[Start],999999)
The formula does not work here.
Here is an example of Phase as Summary Task in Project
- PHASE 4-SITE SEARCH PROCESS
test
The formula only works when the task name is the non-summary task which
isn't the way it is. for example this works:
- test
PHASE 4-SITE SEARCH PROCESS
Is there another test for name for summary tasks?
Thanks
My task level custom date fields stop working when they become summary
tasks. Here is teh formula: IIf([Name]="PHASE 4-SITE SEARCH
PROCESS",[Start],999999)
The formula does not work here.
Here is an example of Phase as Summary Task in Project
- PHASE 4-SITE SEARCH PROCESS
test
The formula only works when the task name is the non-summary task which
isn't the way it is. for example this works:
- test
PHASE 4-SITE SEARCH PROCESS
Is there another test for name for summary tasks?
Thanks