W
Wendy
I am trying to create a project level custom duration field to show the
rollup of durations per phase (specific summary tasks) on a project level.
The issue I am encountering a #Error on the project level code that captures
the task level custom codes for specific phases.
Here are the task level field which work:
Task Level Enterprise Date1 and Enterprise Date2 formulas for start and
finish with calculation for rollup both use formula:
IIf([Name]="PHASE 4-SITE SEARCH PROCESS",[Start],ProjDateValue("NA"))
IIf([Name]="PHASE 4-SITE SEARCH PROCESS",[Finish],ProjDateValue("NA"))
Here is the project level custom duration formula with calculation for
rollup use formula
ProjDateDiff([Enterprise Date1],[Enterprise Date2])
Any help would be greatly appreciated.
Thanks,
Wendy
rollup of durations per phase (specific summary tasks) on a project level.
The issue I am encountering a #Error on the project level code that captures
the task level custom codes for specific phases.
Here are the task level field which work:
Task Level Enterprise Date1 and Enterprise Date2 formulas for start and
finish with calculation for rollup both use formula:
IIf([Name]="PHASE 4-SITE SEARCH PROCESS",[Start],ProjDateValue("NA"))
IIf([Name]="PHASE 4-SITE SEARCH PROCESS",[Finish],ProjDateValue("NA"))
Here is the project level custom duration formula with calculation for
rollup use formula
ProjDateDiff([Enterprise Date1],[Enterprise Date2])
Any help would be greatly appreciated.
Thanks,
Wendy