G
Greg
I have marked company holidays as non-working time on the calendar using
Change Working Time. When I use a fomula in Date1, Date2, etc., it does not
incorporate those non-working time changes. For example, I have Date1 as
starting five days later than Start Date. However, it counts weekends and
holidays as part of the five days.
How do I calculate a date in Date1, Date2, etc that excludes non-working days?
Change Working Time. When I use a fomula in Date1, Date2, etc., it does not
incorporate those non-working time changes. For example, I have Date1 as
starting five days later than Start Date. However, it counts weekends and
holidays as part of the five days.
How do I calculate a date in Date1, Date2, etc that excludes non-working days?