Formula producing odd behaviour

S

Steve Scott

I am testing a RAG status formula which works ok but when I add a task it
erases previous values on tasks above it that it had calcualted prior to the
new task being added. Any ideas?

IIf([Text2]<4,(IIf([Milestone]=-1,IIf([%
Complete]=100,"Complete",IIf(([Baseline Finish]=ProjDateValue("NA") And
[Milestone]=-1),"No baseline
Set!",IIf([Finish]<Date(),"Reforecast",IIf([Number1]>7,"R",IIf([Number1]>0,"A","G"))))),"NM")),"LL")
 
J

JulieS

Hi Steve,

Just a quick thought ....When you are adding the new task, is it a subtask
of the task above it? Do you have the summary tasks using the formula?

Hope this helps. Let us know how you get along.
Julie
 