Formula Question

M

Moonchild

I would like to use the date in finish1 and days in duration1 to calcuate
start1. Can someone please help me with the formual, been working on it
HOURS : )
 
J

Jim Aksel

You could use the DateSub function to determine a date prior to the Finish1
Date:
ProjDateSub( [Finish1], [Duration1])
That would give you Start1

--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 