T
Tamara
I'm setting up a project template. There are several milestones that are set
and I use the "Must Finish On" constraint type. The rest of the tasks use
predecessors to estimate the start date. What I want to do is:
1. Compare the end date of a specific task again a specific milestone
2. "Flag" the task if the dates don't match
Based on my limited knowledge of formulas, when you set up a formula it
works for all tasks. I can't seem to figure out if I can have individual
formulas using the same field.
TIA for your help. -Tamara
and I use the "Must Finish On" constraint type. The rest of the tasks use
predecessors to estimate the start date. What I want to do is:
1. Compare the end date of a specific task again a specific milestone
2. "Flag" the task if the dates don't match
Based on my limited knowledge of formulas, when you set up a formula it
works for all tasks. I can't seem to figure out if I can have individual
formulas using the same field.
TIA for your help. -Tamara